  • 2 Week Construction Lookahead Process Guide plus icon minus icon
  • Purpose The intent of this process is to provide CTA Executives a weekly summary of major, critical and high-risk construction activities throughout the program for the following two weeks. Procedu... See more
  • Authorization to Proceed (ATP) plus icon minus icon
  • Purpose The objective of the Authorization To Proceed process is to track the approvals of CTA Infrastructure Capital Project funding by the CTA Capital Grants, as well as verify the funding has be... See more
  • Concurrence (C) plus icon minus icon
  • The Concurrence process is used to manage and track the request, communication, and disposition of concurrence requests for state-funded CTA project commitments. It is initiated by CTA Purchasing. ... See more
  • Construction Closeout Process (CLOSE) plus icon minus icon
  • The Construction Closeout process is used to manage and track Closeout activities and approvals at the end of a project, including Substantial Completion, Project Element Substantial Completion, Fi... See more
  • Construction Manager Performance Evaluation (CMPE) plus icon minus icon
  • Please click the link below to open the Construction Manager Performance Evaluation (CMPE) guide!   Construction Manager Performance Evaluation (CMPE) guide     See more
  • Consultant Invoice (CI) plus icon minus icon
  • Please click the link below to open the Consultant Invoice process guide!  INF, RPM and RLE Programs  - Consultant Invoice Guide Blanket Contract or Contract Admin (non-cost, non-INF projects) - R... See more
  • Consultant Invoice (Program Manager) (CIPGM) plus icon minus icon
  • Purpose The Consultant Invoice (Program Manager) (CIPGM) process establishes a standard method for processing Program Manager Invoices for Chicago Transit Authority (CTA) Capital Improvement Progr... See more
  • Consultant Performance Evaluation (Construction) (CPEC) plus icon minus icon
  • Please click the link below to open the Consultant Performance Evaluation (Construction) (CPEC) guide!    Consultant Performance Evaluation (Construction) (CPEC) guide See more
  • Consultant Performance Evaluation (Design) (CPED) plus icon minus icon
  • Please click the link below to open the Consultant Performance Evaluation (Design) (CPED) guide!   Consultant Performance Evaluation (Design) (CPED) guide  See more
  • Contract Deliverable Review (CDR) Process Guide plus icon minus icon
  • PurposeThe Contract Deliverable Review (CDR) process provides a structured approach for reviewing contractual deliverables across the planning, design, and construction phases of all project types ... See more
  • Contractor Pay Application Process Guide (I-Pay/R-Pay) plus icon minus icon
  • Here is the guide to for the new Contractor Pay Application Process   Click here for the Contractor Pay Application Process Guide See more
  • Contractor Performance Evaluation (GCPE) plus icon minus icon
  • Please click the link below to open the Contractor Performance Evaluation (GCPE) guide!    Contractor Performance Evaluation (GCPE) guide See more
  • Correspondence (RLE) plus icon minus icon
  • Purpose The Correspondence process is used for routing and review of letters and/or transmittals between CTA and the Contractor, as well as letters to and from third parties.     Procedure Correspo... See more
  • CTA Event Request (CTAER and ERRLE) plus icon minus icon
  • Please click the link below to open the appropriate CTA Event Request process guide for your project!  CTA Event RequestCTA Event Request - RLE Version (ERRLE) See more
  • Design Variation (DVDBB, DVDB, DV) plus icon minus icon
  • Please click the link below to open the Design Variation process guide for your project's delivery method!  Design Variation - Design-Bid-Build (DVDBB) Process GuideDesign Variation - Design-Build ... See more
  • DoR Request for Information (DRFI) & PEC Request for Information (PERFI) plus icon minus icon
  • The DRFI process is used to process requests for information from the designer during the design phase of the project.  The DOR can start the DRFI process.   This PERFI process is to be used for de... See more
  • Engineering Field Report (EFR) plus icon minus icon
  •   The Engineering Field Report process gives CTA Engineering and the Preliminary Engineering Consultant the ability to digitally fill out, submit, and archive form F-EN-306 within e-Builder while c... See more
  • Estimate Approval Process (EAP) plus icon minus icon
  • Purpose Use this process to review and approve estimates that typically route via paper hard copies. Procedure Initiator (01 Estimating Role) uploads & attaches estimate documentation Initiator su... See more
  • Inspector Daily Report Process Guide (IDR) plus icon minus icon
  • Here is the guide for the new Inspector Daily Report Process.**This process also includes the Testing and Inspection Witness Report (TIW) that is spawned from the Inspector Daily Report (IDR) Proce... See more
  • Lessons Learned (LL) plus icon minus icon
  • Objective The purpose of the Lessons Learned Process is to identify, document and analyze events or practices that generate either a positive or negative impact during a project lifecycle. This pro... See more
  • Maintenance Blanket Renewal (MBR) Process Guide plus icon minus icon
  • The Maintenance Blanket Request (MBR) process is an eBuilder process used to submit and monitor renewals for maintenance contracts. The primary purpose of the MBR process is to monitor and track al... See more
  • Manpower Request - Flagger/Towerman (MRFT) plus icon minus icon
  • Please click the link below to open the Manpower Request - Flagger/Towerman process guide!    Manpower Request - Flagger, Towerman See more
  • Manpower Request - Infrastructure (MRI) plus icon minus icon
  • Please click the link below to open the Manpower Request - Infrastructure process guide!    Manpower Request - Infrastructure See more
  • Meeting Minutes Process & Action Items (MMP & MMAIP) plus icon minus icon
  • The Meeting Minutes Process (MMP) provides a structured and standardized approach for creating, reviewing, and distributing official meeting records directly within the Project Website. MMP support... See more
  • Monthly Project & Quarterly Project Updates plus icon minus icon
  •   The Monthly Project Update (MPU) Process captures and tracks project progress on a monthly basis throughout the full project lifecycle. The MPU Process Guide - Provides an overview of the MPU Pr... See more
  • Non-Conformance Report (NCR) plus icon minus icon
  • Purpose Use this process to route Non-Conformance Reports for Response, Review, and Implementation of Corrective Action (if applicable). Procedure The NCR workflow is divided into 4 paths based on ... See more
  • Overhead Adjustment Reconciliation plus icon minus icon
  • Objective The Overhead Adjustment Reconciliation (OAR) process will be used to route overhead adjustment reconciliations in e-Builder. Audit submissions will still be done outside of e-Builder and ... See more
  • Potential Change Order (PCO) & Change Order (CO) Process Guide plus icon minus icon
  • The new, electronic Potential Change Order (PCO) and Change Order (CO) process was developed to implement electronic change management processes for Construction Contracts, providing transparency f... See more
  • Project Initiation Process Guide (PIF) plus icon minus icon
  • Here you will find the guide for the new e-Builder Process Project Initiation Form (PIF).  The reasons to use this process are:  Add a new project into e-Builder (Approval Required)  Edit/Update E... See more
  • Project Membership Request (PMR) plus icon minus icon